Inspection Details
—
Submitter:
—
Team:
—
Teammate:
—
✓ Location Successfully Recorded
Serial Numbers
CFX
CFZ
CFD
Versions
Lock-Out / Tag-Out (LOTO)
This LOTO Control Form is filed to the LOTO board. Project, tower, and date carry over from this inspection. One technician runs the procedure for each tower.
—
—
—
Tick what was released or restrained. Blank is recorded as blank, never as “no”.
The permit calls this the single most-skipped step. Anything left unanswered stays unanswered.
Locks Applied
Tap to add
Everyone working under this isolation signs twice: an acknowledgement now, as the locks go on, and a release later when they come off. Up to 8 people.
Photos
Inspection Checklist
0 of 22 checked
Inspection Findings and Repairs
End LOTO Procedure
Finish the inspection work first. Ending the procedure pauses your teammate again while the locks come off and everyone signs the release.
Locks Removed
Tap to add
Everyone who acknowledged this isolation signs again now that the locks are off.